Wednesday, August 16, 2006

Earthwork complete


Spoke with the grading contractor early yesterday - earthwork would be complete yesterday before noon. All that remained was some minor trimming of the graded pad and placing some fill for the driveway (to elevate it above adjacent grade for drainage reasons).

I need to look into getting aggregate base and asphalt placed, but will probably wait until concrete is placed for the floor slab. The fewer heavy trucks running over it the better. I think I have a good recommendation - I need to veryify and follow up.

Here is a picture of our son next to the earthwork contractor's tractor. He thought it was pretty cool.

No comments: