Tuesday, August 22, 2006

Well, the general contractor said that he takes care of getting the power and phone hookups scheduled/co-ordinated, so that should be taken care of at the proper time. He also has the fire department reviewing the plans and creating a fire sprinkler layout for the inside of the house (required in county areas).

Still waiting on the plan corrections from the architect - he should probably finish later this week or early next week. Then resubmittal to the county, and hopefully we're done. ***crosses fingers***

We need to start making a few more decisions on items like the front door, fixtures, etc, as those things will impact the final house price and we'd like to be able to assign a firm number instead of a generic allowance. We already have appliances, gas fireplace, gas tankless water heaters (two in parallel for increased simultaneous hot water use capability), countertops, roofing, and a good portion of the cabinetry chosen, so that helps. We also have siding and stucco planned (siding for the front, stucco in the rear). Window type and brand has been chosen, as has general flooring type.

We're getting there, it just takes a while.

Sunday, August 20, 2006

We went out to take a look at progress on the building pad - pad itself is done and the grading contractor has placed some fill on the driveway area and compacted it to raise it a little above grade.

Our little guy likes the dirt - nothing better than 5 acres of soil and a Tonka truck!

Thursday, August 17, 2006

Plans back to architect

I returned the plans to the architect this morning with the county review comments and our own corrections. He thinks they (architectural, structural, and energy calculation revisions) should be finished within a week or so and ready for resubmittal.

Our contractor is currently working on another house and hopes to be finishing up that one by the first week or so of October. We may be breaking ground in under two months if this is the case.

I need to find out about getting electric and phone service to the site.

Wednesday, August 16, 2006

Earthwork complete


Spoke with the grading contractor early yesterday - earthwork would be complete yesterday before noon. All that remained was some minor trimming of the graded pad and placing some fill for the driveway (to elevate it above adjacent grade for drainage reasons).

I need to look into getting aggregate base and asphalt placed, but will probably wait until concrete is placed for the floor slab. The fewer heavy trucks running over it the better. I think I have a good recommendation - I need to veryify and follow up.

Here is a picture of our son next to the earthwork contractor's tractor. He thought it was pretty cool.

Monday, August 14, 2006

Earthwork Underway

Driveway culvert pipe is in and the ditch has been backfilled. Placement of aggregate base and asphalt will be later - no point in accidentally tearing up asphalt during construction. Photo is looking to the south.


The building pad is being graded and is almost complete. Top of pad elevation is about 2 feet above original grade. The pad should be done within another day or two.

Here's a couple shots of the site as well. The house to the right in the second photo is my sister's place. First photo is looking to the west, the second to the northwest.